Meldan Assigned Two Key Shutdowns Simultaneously - 09/04/2009 |
|
Meldan had carefully planned one main shutdown and delivered pre-shutdown work leading upto the White Oils Major turnaround for a Major Refinery in April for 30-40 Men for 28 Days. Meldan were then suddenly appointed after a breakdown elsewhere on the other side of the Refinery a seperate shutdown for 44 days on the Calciner. The company had to respond quickly and resource, engineer and manage 20-30 key personnel to enable delivery of this given 2 days notice. |
|
|
|
|
|
|
|